The project will have an installed capacity of 400 MW to supply electricity to the surrounding provinces as well as for export to Vietnam. The project is Build Operate and Transfer (BOT) type and the investment cost is USD 816.23 million. The main dam length is 8km with crest 83m above the sea level and about 40m above the river. There are 5 turbine units with a capacity of 80MW each.
Thông tin khác
Miền | Giá trị |
---|---|
Cập nhật lần cuối | 4 tháng 10, 2021 |
Được tạo ra | Không biết |
Định dạng | |
Giấy phép | unspecified |
Tên | 10. Annex [Part 1] |
Các ngôn ngữ của tài nguyên |
|
Mô tả | The project will have an installed capacity of 400 MW to supply electricity to the surrounding provinces as well as for export to Vietnam. The project is Build Operate and Transfer (BOT) type and the investment cost is USD 816.23 million. The main dam length is 8km with crest 83m above the sea level and about 40m above the river. There are 5 turbine units with a capacity of 80MW each. |