DWIR_ESIA Report on Twante Canal Improvement Project
Published by: Open Development Myanmar
Data Resources (3)
Data Resource Preview - ESIA of Twante Canal Improvement Project of DWIR
Thông tin khác
Miền | Giá trị |
---|---|
Vùng địa lý (phạm vi không gian) |
|
Chủ đề | Environmental impact assessments |
Loại tài liệu | Environmental Impact Assessment |
Các bên ký kết |
|
Đối tượng thuộc chính phủ (nhiều) |
|
Chế dộ tiết lộ | Released by government |
Giấy phép |
No license given |
Bản quyền | No |
Hạn chế truy cập và sử dụng |
By accessing this website or database, users agree to take full responsibility for reliance on any site information provided and to hold harmless and waive any and all liability against individuals or entities associated with its development, form and content for any loss, harm or damage suffered as a result of its use. |
Phiên bản/ Ấn phẩm | 1 |
Ngôn ngữ của tài liệu |
|
(Các) Tỉnh |
|
Liên kết đến nguồn | http://www.ecd.gov.mm/?q=policy |
Party's obligation in the implementation of the project |
The project owner shall earnestly carry out all national and local laws, regulations and requirements on environmental protection, clearly define main duties and responsibilities of environmental protection departments of the project, establish and optimize its rules and regulations. |
Environmental protection obligation |
The project commits to precisely follow the discussed mitigation measures for avoiding or reducing such environmental and socioeconomic impacts generated in temporarily or permanently by the Project activities during both the construction and operation phases. |
Socio-cultural protection |
The project commits to engage the affected community and any project stakeholders in, adequate manner and meaningfully consult them for any environmental and social issues related to the project activities. Land acquisition and resettlement action plan, and grievance redress mechanism will also be done. |
Environmental fund summary |
During the construction phase, a budget of about US$ 53,370 equivalents per year will be allocated for monitoring and evaluation of the Project’s environmental and social performance over the construction period of 5 years. During the operational phase, an annual budget of about US$ 25,850 will be allocated for monitoring activities. |