[Draft] Preliminary environmental and social impact assessment: Project investment on agro-industrial plantation (rubber)
Published by: Open Development Cambodia
Data Resources (11)
Data Resource Preview - 01. Table of contents
Thông tin khác
Miền | Giá trị |
---|---|
Vùng địa lý (phạm vi không gian) |
|
Chủ đề |
|
Loại tài liệu | Environmental Impact Assessment |
Các bên ký kết |
|
Đối tượng thuộc chính phủ (nhiều) |
|
Chế dộ tiết lộ | Released by local non-governmental organizations (LNGOs) |
Giấy phép |
No license given |
Bản quyền | No |
Hạn chế truy cập và sử dụng |
By accessing this website or database, users agree to take full responsibility for reliance on any site information provided and to hold harmless and waive any and all liability against individuals or entities associated with its development, form and content for any loss, harm or damage suffered as a result of its use. |
Phiên bản/ Ấn phẩm | 1 |
Ngôn ngữ của tài liệu |
|
(Các) Tỉnh |
|
Thông tin tham khảo Metadata. |
Metadata last updated on 2018-06-12. For inquiries contact: Open Development Cambodia, Email: contact@opendevcam.net, Website: http://www.opendevcam.net Address: 43 St. 208, Phnom Penh, Cambodia. |
Liên hệ |
Green Consultancy Firm Address: No. 24B, St. 218, Sangkat Teuk Laok 3, Khan 7 Makara, Phnom Penh, |
Khu vực được cấp phép | 8100.0 |
Điều khoản hợp đồng | 20.0 |
Đơn vị điều khoản hợp đồng | Years |
Job creation summary |
The company needed 984 of local employees including worker, technician and manager for the first year and would increase by 1,011 in the fifth year. From the sixth to tenth years, the company would need labour force approximately 1,016 people for this production. |
Training summary |
The company were planning to train those cambodian employees 01 to 03 months or more in accordance with the needs. In addition, the employees could learn practically from experts on the field |
Environmental protection obligation |
This environmental management planning project did not require involvements from other establishment due to the negative impacts caused by the development are minimal. However, the company must principally responsible for the environmental management in accordance with environmental management measures as defined by ESIA report. |
Socio-cultural protection |
The company made an assessment on the social impacts regarding several factors such as social resource, health and safety impact, regional and cumulative effects. Along with these assessment, the company has pointed out measures for the mitigation. |
Environmental fund summary |
The budget allocated for environmental management planning implementation for a period of 9 years require 3,081,500 USD. This budget is for: (1) infrastructure construction, (2) buffer zone management, (3) contribution fund for development of community and environmental restoration, and (4) investigation and assessment implementation. |
Tổng số tiền của quỹ môi trường | 3081500.0 |
Dự án liên quan | |
Tài liệu tham khảo kế thừa | Draft_EIA_Tan_Bien_Kampongthom_apivath_caoutchouc__00.07.2011.pdf |
Các từ khóa | rubber plantation,agro-industrial plantation,Kampong Thom,environmental impact assessment |
Định danh hợp đồng mở | ocds-miumsd-68361c50-2756-4f3d-89ff-8948c9a48254 |
Ngày đăng tải | tháng 1 3, 2020, 07:16 (UTC) |
Ngày chỉnh sửa, cập nhật | tháng 10 11, 2021, 02:38 (UTC) |